- January 8, 2024 Minutes
- January 22, 2024 Minutes
- February 12, 2024 Minutes
- February 26, 2024 Minutes
- March 11, 2024 Minutes
- March 25, 2024 Minutes
- April 8, 2024 Minutes
- April 22, 2024 Minutes
- May 13, 2024 Minutes
- May 28, 2024 Minutes
- June 10, 2024 Minutes
- June 24, 2024 Minutes
- July 8, 2024 Minutes
- July 22, 2024 Minutes
- August 12, 2024 Minutes
- August 26, 2024 Minutes
- September 9, 2024 Minutes
- September 23, 2024 Minutes
- October 14, 2024 Minutes
- October 28, 2024 Minutes
- November 12, 2024 Minutes
- November 25, 2024 Minutes
- December 9, 2024 Minutes
Category: Authority
Board Meeting Time Change Effective 09/23/2024
On September 9, 2024 during the regularly scheduled Spring-Benner-Walker Joint Authority Board Meeting, a motion was passed to change the time of the Board Meetings from 7:00 p.m. to 4:00 p.m. starting with the next regularly scheduled Board Meeting on September 23, 2024. A legal notice with the new meeting schedule has been advertised with The Lock Haven Express.
If you have any questions regarding this new change please contact our Authority office at 814-355-4778.
Thank you.
2023 Meeting Minutes
- January 9, 2023 Minutes
- January 23, 2023 Minutes
- February 13, 2023 Minutes
- February 27, 2023 Minutes
- March 13, 2023 Minutes
- March 27, 2023 Minutes
- April 10, 2023 Minutes
- April 24, 2023 Minutes
- May 8, 2023 Minutes
- May 22, 2023 Minutes
- June 12, 2023 Minutes
- June 26, 2023 Minutes
- July 10, 2023 Minutes
- July 24, 2023 Minutes
- August 14, 2023 Minutes
- August 28, 2023 Minutes
- September 11, 2023 Minutes
- September 25, 2023 Minutes
- October 9, 2023 Minutes
- October 23, 2023 Minutes
- November 13, 2023 Minutes
- November 27, 2023 Minutes
- December 11, 2023 Minutes
Application for Employment
Please choose between printing an employment application to fill out and return to our Authority office at 170 Irish Hollow Road, Bellefonte, PA 16823 or by email to [email protected] or fill out the fillable PDF and email it to [email protected]
Quarterly Rates
$75.00 per EDU (equivalent dwelling unit) per Quarter. Offer a 5% discount for yearly payments
Resolution 2021-02
Effective with the 1st Quarter 2022 billings, the Spring Benner Walker Joint Authority’s sewer usage rates will increase from $70.00 per EDU per quarter to $75.00 per EDU per quarter. Resolution 2021-02 that was approved at the November 22, 2021 meeting is attached.
Act 537 – Shiloh Road
In April of 2019, the Benner Township Supervisors directed the Spring Benner Walker Joint Authority (SBWJA) to extend public sewer from the existing system at the University Park Airport to the Shiloh Road interchange. This directive required a special study to be completed to update the Township’s existing 537 Plan through the Pennsylvania Department of Environmental Protection (PA DEP). The study was completed and presented for public comment during Benner Township’s public meetings in November and December of 2019 with final Township approval occurring in January 2021.
There was significant interest in this project and numerous meetings were held to discuss concerns by affected residents. Following numerous public meetings, the idea of this sewer extension was well vetted; however, a court challenge ensued and some of the local concerns were brought before the Environmental Hearing Board (EHB) in Harrisburg. Following a three-day hearing, the EHB dismissed all remaining local concerns and ruled that both SBWJA and Benner Township followed the Act 537 regulations while preparing this special study.
The path has now been cleared to proceed with this extension as originally planned. The schedule of construction has been adjusted due to these delays and will now proceed as follows. The SBWJA will obtain all necessary permits from the various agencies of the Commonwealth through the fall of 2024. The project is extensive and requires work in some sensitive environmental locations along the proposed layout. A pre-permit meeting was held with PA DEP where we discussed the safest approach for the temporary construction within the environmentally sensitive areas. Once these permits are obtained, the SBWJA will move forward with the bidding process to hire a contractor that will complete this work.
SBWJA currently plans to open bids in early 2025 and provide notice to proceed with the contractor chosen to begin immediately. SBWJA believes the project will be substantially complete by the fall of 2025 when new customers will be able to begin connecting to the new extension.
Several developers have contacted the SBWJA regarding this extension and we believe development in the Shiloh Road interchange area will quickly follow the completion of this project. Additionally, the homes that currently exist in this fragile, environmentally sensitive area will be served by public sewer eliminating the discharge of pollutants into Spring Creek while protecting this pristine trout stream for future generations.
If you have any questions or concerns, please don’t hesitate to contact our Authority office.
Downloads: